Construction of Croatia’s new national football centre in Velika Gorica is progressing, with work advancing across the stadium, administrative building and training facilities, according to a report from Croatia Week. The federation expects the complex to be completed next summer.
Croatian Football Federation (HNS) president Marijan Kustić visited the site with general secretary Josip Tomaško and other federation officials and staff to inspect the latest progress, the report said.
Stadium and training facilities
The centre will feature a stadium with a capacity of 1,500 spectators, a natural-grass main pitch, a fully equipped fitness centre and six changing rooms. The wider complex will also include two additional natural-grass pitches and one artificial-grass pitch, intended to support national team preparation as well as wider development of the game in Croatia.
Administrative building
According to the report, construction and installation work on the administrative building has been completed and interior finishing is under way. The building will house the HNS leadership and administration, the football development department, the refereeing organisation and the HNS Football Academy, along with a conference hall and additional meeting and education rooms.
Timeline
Andrea Dokuš, head of infrastructure at HNS, was quoted in the report saying that finishing work continues at the stadium, including walls, ceilings and flooring, while groundwork, drainage and irrigation are progressing across the pitches. Dokuš said the project remains on schedule for completion by summer 2027.
Kustić expressed satisfaction with the progress and thanked contractors, supervisors, federation staff and construction workers. He said the centre would give administrative, professional and sporting departments a shared working environment alongside the national teams, coaches and players.
Football Maza is reporting on the project based on the Croatia Week account, which describes the centre as the federation’s most significant infrastructure project to date.